It is planned to accommodate 1000 hospital beds for patients diagnosed with Corona/COVID-19.
The work was to be completed in 45 days, starting in April. The buildings would require over 200 air handling units and Regin provides a solution including control panels, controllers, pressure transmitters etcetera.
“Thanks to dedicated employees and shift work on our production site in Istanbul, we managed to deliver 80 percent of the control panels in 14 days. We are extremely happy and proud to be able to contribute with products and solutions that make a difference during these special times” says Lasse Bornö, Group Business Development Manager Key Accounts, at Regin.